Work anticipated week of 5/31/21
* Please note all work is weather dependent
Tuesday there will be a water shut down to allow the Contractor to lower the water main on Indiana Ave. Lowering the water main is necessary to accommodate the new culvert.
Sanitary sewer installation will begin on Walnut Ave and continue east to 10th Ave.
Excavation and preparations for the new box culvert will take place all week.
Grading and excavation will be ongoing between Indiana Ave. and Illinois Ave.