Update - 5/13/22

Anticipated work for the next week: 

5/12 – Final Curb Section on Walnut

5/13 – Milling and prep for paving

5/16- Paving Binder Course

5/17 – Manhole Adjustments

5/18 – Manhole Adjustments

5/19 – Paving Surface Course

5/20 – Pavement Patches

Parkway restoration was started on 5/12/22 and will continue until finished