Update - 8/31/17

Anticipated construction work for September 7th through September 10th:

A road closure of 37th Avenue, between Illinois Avenue and Ohio Avenue, is scheduled for Thursday evening, September 7th through Sunday, September 10th, to allow for pavement removal, base reclamation and paving the asphalt binder and surface.  The road will be open to traffic for business operations on Monday, September 11th.

Update - 8/31/17

Anticipated work for the week of September 1-8:  The Contractor will be installing steel piles and constructing the new concrete retaining wall.   Please continue to be alert for lane closures and flaggers!

Update - 8/28/17

Solar installation mostly completed.  Substation civil work 90% completed.  Substation transformer on order, delivery due in November 2017.  Other major substation equipment on order or in the specification/bidding process.  Substation still planned to go into service prior to summer of 2018.

Update - 8/16/17

Road Closure Alert:  38th Avenue will be closed to traffic between Illinois Avenue and Ohio Avenue, beginning Thursday evening, August 17th through Sunday, August 20th, to allow for pavement removal, base reclamation and paving the asphalt binder and surface.  The road will be open to traffic for business operations on Monday, August 21st.