Update - 6/15/23
Anticipated construction work for the week of June 18 – June 24
Please Note: All work contingent on weather
East Side Streets
East Side Streets
More good weather for construction has allowed for forward progress on the demolition of the existing switchback ramps near the Riverwalk and placement of aggregate base for the new ramp is in progress. Underground utility work is up next and will continue for the next few weeks in conjunction with the beginning of foundations for site improvements such as the steel trellis structure and associated underground infrastructure.
East Side Streets
East Side Streets
Mother nature has given the gift of very good construction weather and this week lots of progress was made toward completing the demolition portion of the project. Removal of the walls and ramps to the river walk is in progress and crews have completed a substantial portion of the demolition work which means it’s almost time to start building! Keep checking for updates as we are anticipating starting on building foundations to support the new plaza features in the near future.
Please Note: All work contingent on weather
East Side Streets
Demolition of the existing South 1st Street concrete paving is complete! Removal of the concrete paving, sidewalks, planter boxes and other items from Main Street to Walnut Street has been completed and crews are moving on to sidewalks, bricks and planters on the east side of the road with plans to start the demolition process on the existing river walk ramp next. A reminder that this area is a construction zone and not open to the public. However, please enjoy the process and views from behind the construction fence and keep up with our progress toward this exciting new feature in the h
East Side Streets