Ward 3

Week of October 15, 2012

The Contractor is expected to continue with the excavation of the new roadway widening. Work is expected to be completed on Tyler Road by Wednesday of this week. Excavation work will then begin between S. 13th Avenue moving east towards the McGrath Honda Dealership. This work is expected to continue through the rest of this week being completed by Tuesday of next week.

To read the complete update, download the attached document. 

Week of September 24, 2012

The Contractor will also begin prepping and placing the subgrade and sub-base of the new roadway from Powis Road to Smith Road on the north side of East Main Street. This work is expected to take place over the next two weeks. Once the sub-base of the new roadway has been completed the Contractor will begin placement of an asphalt cap over the new sub-base.

To read the full update, download the attached document.

Week of September 17, 2012

Due to modifications to the existing grading elevations near the intersection of Kautz Road and East Main Street, the Contractor will be closing the intersection at Kautz Road and East Main Street for one day beginning Tuesday September 18 at 6:00 am. This intersection is expected to be reopened by 5:00 pm the following day.

To read the full update, download the attached document.

Week of September 10, 2012

 
The Contractor will continue working on the rebuilding of the new roadway from Powis Road to Kautz Road on the south side of East Main Street. This work is expected to take place over the new 4-5 weeks. The Contractor will continue to work on the preparation of the subgrade and sub-base materials for the new widening section from Powis Road to Smith Road.
 
To read the full update, download the attached document.

 

Week of August 27, 2012

The Contractor will continue the transferring of water services on the new water main installed near Dunham Road heading east on East Main Street for approximately 1000 feet. This work is expected to be completed by the end of the week. Local businesses may experience temporary water shut-offs during this time. Public Works crews will be providing additional notification prior to these interruptions.

To read the full update, download the attached document.

Week of August 20, 2012

The Contractor will be working on the replacement of an existing storm box culvert just west of the intersection of East Main Street and 9th Avenue. This work will also include the modification to the existing outfall pipes discharging into the North Tributary Creek. This work is expected to be completed in the next few weeks.

To read the complete update, download the attached document.

Week of August 13, 2012

Lane reductions near the intersection of East Main Street and Dunham Road will continue this week for work associated with the installation of the new water main and utility work on the north side of East Main Street. The construction limits for this work are from Dunham Road heading east for approximately 1,000 feet.

To read the complete update, download the attached document.

Week of July 30, 2012

Two crews continue to work on the installation of the new water main from 7th Avenue towards Hunt Club Drive. Crews will primarily be focusing on the installation of new water services for local businesses and homeowners. Temporary water shut-downs will be encountered during this work. City water crews will be working on providing proper notification prior to this work taking place.  To read the complete update, download the attached document.