Week of June 30, 2014
Phase One utility repairs have been completed on Squire Lane, Foxfield Drive, Frontage Road, Kehoe Street, Alice Court and Margaret Court, and are in progress on Ash Street, McKinley Street and Ohio Avenue this week.
Phase One utility repairs have been completed on Squire Lane, Foxfield Drive, Frontage Road, Kehoe Street, Alice Court and Margaret Court, and are in progress on Ash Street, McKinley Street and Ohio Avenue this week.
Phase One utility repairs are continuing on Squire Lane, Foxfield Drive, Frontage Road, Kehoe Street, Alice Court, Margaret Court and Ash Street.
Utility repairs are planned to begin on Ohio Avenue and McKinley Street this week.
Phase One utility repairs have been completed in Cambridge East neighborhood, and have started on Squire Lane, Foxfifeld Drive, Frontage Road, Kehoe Street, Alice Court and Margaret Court. Utility repairs are planned to begin on McKinley Street this week.
The main section of the biosolids and operational building is now completed. This section houses liquid storage, chemical storage, pumping and dewatering equipment along with the new Motor Control Center and plant power distribution. Equipment has been through start-up procedures with staff training. Most equipment is now operational and running on a daily basis.
Water main installation, hydrant replacements, water service connections, testing and restoration of the parkway have been completed on South 19th Street & Walnut Drive Water Main Improvement Project.
Phase One utility repairs have started on Cambridge Drive, Cambridge Court, Jeanette Avenue, Midway Avenue and Cumberland Green Drive as of May 30.
The 2014 MFT Street Rehabilitation Project has been awarded to Hardin Paving Services, from Hillside, Illinois.
Phase One utility repairs are anticipated to begin on Cambridge Drive, Cambridge Court, Jeanette Avenue, Midway Avenue and Cumberland Green Drive on Tuesday, May 27, 2014.
The MFT Project will include Hot Mix Asphalt pavement removal and replacement, curb and sidewalk repairs, public utility repairs, parkway restoration, and other appurtenant work for a complete improvement.
Construction on South 19th Street & Walnut Drive Water Main Improvements is scheduled to begin on Monday April 14, with an anticipated completion by the end of May. The work will take place along the west side of South 19th Street between West Main Street and Walnut Drive, and 200 feet west along the north side of Walnut Drive. The contract for this project has been awarded to Martam Construction, Elgin IL.
Construction on South 19th Street & Walnut Drive Water Main Improvements is scheduled to begin on Monday April 14, with an anticipated completion by the end of May. The work will take place along the west side of South 19th Street between West Main Street and Walnut Drive, and 200 feet west along the north side of Walnut Drive. The contract for this project has been awarded to Martam Construction, Elgin IL.
As part of an ongoing commitment to maintain City owned facilities, last year, the Public Services Division completed an exterior conditions analysis of the Municipal Building at 2 E. Main Street. The analysis was performed by a local architectural-construction firm, the Prairie Forge Group. This analysis was a study of the building’s exterior shell and resulted in identifying key deficiencies that required repairs to keep the structure weather-tight.