Week of August 10, 2015

West Side of Fox River

Avalon Court
No work this week.

8th Street and 8th Court
No work this week.

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week.

East Side of Fox River

Walnut Ave. 
Concrete pavement base. HMA pavement grinding. Brick sidewalk repair.

Crabapple Ln.
No work this week.

S. 10th Ave
Concrete sidewalk repair.

Week of August 3, 2015

The work completed for the week ending August 1, 2015 included starting on the Marion Avenue connection as well as the fire hydrant installation at this location.  Flushing and pressure testing of the new watermain has begun.  The contractor has begun restoration of curb and gutter.

Week of August 3, 2015

West Side of Fox River

Avalon Court
Paving complete, Restoration September 1st.

8th Street and 8th Court
Paving complete, Restoration September 1st.            

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Paving complete, Restoration September 1st.

East Side of Fox River

Walnut Ave.
No work this week.

Crabapple Ln.
Paving complete, Restoration September 1st.

Week of July 27, 2015

West Side of Fox River

Avalon Court
Hot Mix Asphalt, leveling binder and crack prevention material

8th Street and 8th Court
Hot Mix Asphalt, leveling binder and crack prevention material               

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Hot Mix Asphalt, surface and crack prevention material

East Side of Fox River

Walnut Ave.
Concrete street repair and patching

Week of July 27, 2015

The work completed for the week ending July 25, 2015 included the Allen Lane connection as well as the fire hydrant installation at this location. The connection at North Avenue was also completed with the associated fire hydrant.  Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts. Contractor has begun restoration of curb and gutter.

Week of July 20, 2015

The work completed for the week ending July 18, 2015 included fire hydrant installation at Allen Lane on 5th Avenue. Connections were also completed this week at connections at Delnor, private drive and Marion.  Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts.

Week of July 20, 2015

Work for the week of July 20 is scheduled as follows:

Concrete curb and sidewalk saw cutting, forming and pouring new concrete curb and sidewalks

Utility structure adjustments

Pavement grinding and pavement patching, mid-week through the end of the week

Week of July 20, 2015

West Side of Fox River

Avalon Court
Pavement Grinding, Pavement Patching and Driveway Apron Repairs

8th Street and 8th Court
Pavement Grinding, Pavement Patching and Driveway Apron Repairs                   

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Pavement Grinding, Pavement Patching and Driveway Apron Repairs       

East Side of Fox River

Walnut Ave.
Utility work in street. (Replacement of water main structures)

Week of July 13, 2015

The work completed for the week ending July 11, 2015 included the continued installation of fire hydrants and valve vaults along 5th Avenue. The Stonehedge Road and North Avenue side street connections were also completed this week.  Flushing and pressure testing of the new watermain has been postponed until correct parts are obtained.

Week of July 13, 2015

WEST SIDE OF FOX RIVER

Avalon Court
Curb and sidewalk removal and replacement

8th Street and 8th Court
Curb and sidewalk removal and replacement
Utility work in street (Replacement of storm sewer structures)

Greenwood Lane, Mockingbird Court and Oxmoor Court
Curb and sidewalk removal and replacement

EAST SIDE OF FOX RIVER

Walnut Avenue
Utility work in street (Replacement of water main structures)

Crabapple Lane
Curb and sidewalk removal and replacement