You are here

Week of June 15, 2015

The work completed for the week ending June 13, 2015 included installation of watermain from Allen Lane south along the east side of 5th Avenue to the end of the project at North Avenue.  Side street watermain installations at Iroquois Avenue, Allen Lane and Delnor Avenue are complete except for testing and pavement restoration.  Installation of valve vaults continued this week with the installation of 6 vaults.  Fire hydrant installation began on the 5th Avenue watermain this week.

The scheduled work for the week ending June 20, 2015 will include installation of valve vaults and fire hydrants on the 5th Avenue watermain.  Pressure testing and chlorination of the watermain will begin mid-week.  The contractor will provide notifications to those residents affected by construction who may have restricted access to their driveways during this work 48 hours in advance.  

All work schedules are weather dependent.  Daily lane closures should be expected on IL Route 25 for the above work this week.

created Jun 11, 2015 updated Mar 23, 2018