MetroNet, a Midwest fiber optic service provider, delivering high-speed gigabit Internet, high-definition television and phone service recently announced expansion into St. Charles, Illinois. MetroNet serves more than 30 communities in Indiana and Illinois.
MetroNet currently is installing/constructing their fiber network. Some frequently asked questions about the network construction phase:
Does MetroNet have the proper permits for the construction they are about to perform?
Avalon Court
Completed – Punchlist items outstanding
8th Street and 8th Court
Completed – Punchlist items outstanding
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed
Walnut Ave.
Completed – Punchlist items outstanding
Crabapple Ln.
Completed – Punchlist items outstanding
S. 10th Ave
Completed – Punchlist items outstanding
Stone Dr. and DuKane Dr.
Avalon Court
Minor sidewalk repair.
8th Street and 8th Court
Completed – Punchlist items outstanding.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed
Walnut Ave.
Completed – Punchlist items outstanding.
Crabapple Ln.
Minor sidewalk and curb repair.
S. 10th Ave
Completed – Punchlist items outstanding.
Stone Dr. and DuKane Dr.
Tyler Road
The work completed for the week ending September 5, 2015 included the installation of watermain from Allen Lane south to Wing Lane. Flushing and pressure testing of the watermain began on the north end of the project.
The scheduled work for the week ending September 12, 2015 will include the continued installation of watermain to the south.
Avalon Court
No work this week. Restoration 1st and 2nd week of September.
8th Street and 8th Court
No work this week. Restoration 1st and 2nd week of September.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week. Restoration 1st and 2nd week of September.
Avalon Court
No work this week
8th Street and 8th Court
No work this week
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week
Walnut Ave.
Hot Mix Asphalt roadway surface pavement paving.
Crabapple Ln.
No work this week.
S. 10th Ave
Hot Mix Asphalt roadway surface pavement paving.
Avalon Court
No work this week.
8th Street and 8th Court
No work this week.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week.
Walnut Ave.
Hot Mix Asphalt pavement grinding.
Hot Mix Asphalt pavement paving.
Crabapple Ln.
No work this week.
S. 10th Ave
Hot Mix Asphalt pavement grinding.
Hot Mix Asphalt pavement paving.