You are here

Week of July 13, 2015

The work completed for the week ending July 11, 2015 included the continued installation of fire hydrants and valve vaults along 5th Avenue. The Stonehedge Road and North Avenue side street connections were also completed this week.  Flushing and pressure testing of the new watermain has been postponed until correct parts are obtained.

The scheduled work for the week ending July 18, 2015 will include the continued installation of valve vaults and fire hydrants on the 5th Avenue watermain.  Side street connections at Allen Lane and Marion Avenue will be completed this week.  The contractor will provide notifications to those residents affected by construction who may have restricted access to their driveways during this work 48 hours in advance.

All work schedules are weather dependent.  Daily lane closures should be expected on IL Route 25 for the above work this week.

 

created Jul 13, 2015 updated Mar 23, 2018