Update - 7/11/17

The grading for the solar site is completed, and solar panel deliveries are expected in the next two weeks.  Solar production is scheduled to begin in August or September.

Inside the substation, the majority of the site work is done and equipment for the substation is beginning to be set.  Substation target completion and in-service in spring of 2018.