Update - 6/21/18

Next week the contractor will perform the following:

All streets:  Sawcutting of curbs, sidewalks and impacted driveways.

Adams Ave/Ct: No additional work anticipated.

Dover Hill Ct:  No additional work anticipated.

Fox Chase Dr:  Utility repairs and concrete removal and replacements may begin.

Jackson Ave:  No additional work anticipated.

Jewel Ave:  Utility repairs may begin.

N. 12th Ave:  Utility repairs to begin.  Expect a mid-block road closure.  Look for notice early next week.

Mildred Ave:  No additional work anticipated.

Persimmon Dr:  No additional work anticipated.

Rita Ave:  No additional work anticipated.

Ronzheimer Ave:  Utility repairs and concrete removal and replacements to begin.

Ruth Ave:  No additional work anticipated.

Spring Ave: No additional work anticipated.