Update - 7/20/18

Next week the contractor will perform the following:

Adams Ave/Ct: Utility repairs may begin.
Dover Hill Ct:  Utility repairs may begin.
Fox Chase Dr:  Driveway replacements to continue.
Jackson Ave:  No work anticipated.
Jewel Ave:  Concrete work to continue.
N. 12th Ave:  Concrete work to continue.
Mildred Ave:  Utility repairs to begin.  Concrete work may begin.
Persimmon Dr:  Concrete work may begin.
Rita Ave:  Utility repair work to begin.  Concrete work may begin.
Ronzheimer Ave:  Driveway replacements to continue.
Ruth Ave:  Concrete work to continue.
Spring Ave: No work anticipated.

 