Next week the contractor will perform the following:
Adams Ave/Ct: Utility repairs may begin.
Dover Hill Ct: Utility repairs may begin.
Fox Chase Dr: Driveway replacements to continue.
Jackson Ave: No work anticipated.
Jewel Ave: Concrete work to continue.
N. 12th Ave: Concrete work to continue.
Mildred Ave: Utility repairs to begin. Concrete work may begin.
Persimmon Dr: Concrete work may begin.
Rita Ave: Utility repair work to begin. Concrete work may begin.
Ronzheimer Ave: Driveway replacements to continue.
Ruth Ave: Concrete work to continue.
Spring Ave: No work anticipated.