Update - 08/03/17
Anticipated construction work for the week of August 7 - August 11:
Anticipated construction work for the week of August 7 - August 11:
Work continues on the solar plant. The racks for the solar panels are 75% installed. Work on the substation fence, other minor substation items, and landscape restoration will commence after the solar plant installation is completed.
The solar plant is expected to be connected to the grid and feeding power to St. Charles in September, even though some of the elements of the substation will not be completed until spring of 2018.
The last of the pavement work started today. The right southbound lane is closed for the final concrete pavement curing. The work is scheduled to be 100% complete on Monday, August 7.
Anticipated construction work for July 28th through August 4th:
Anticipated construction work for the week of July 31- August 4:
Pavement rejuvenation is scheduled to begin the first week of August. Individual notices will be provided to impacted property owners with additional information.
Anticipated construction work for July 21st through July 28th:
Anticipated construction work for the week of July 24-28:
Friday, July 14th thru Friday, July 21st - The contractor will continue concrete curb, sidewalk and driveway replacements and begin utility repairs. Each business with proposed driveway repairs will be contacted to coordinate the work and property access.
Anticipated construction work for the week of July 17-21: