Update - 5/7/21
Anticipated construction work for the week of May 10-14
Please Note: All work contingent on weather
Anticipated construction work for the week of May 10-14
Please Note: All work contingent on weather
Week of 5/10/21
Final grading and restoration south of South Ave.
Concrete curb and gutter on South Ave.
Grading between South Ave. and Indiana Ave.
Sanitary sewer on 10th Ave.
Water main construction on this project has been completed. Over the next two weeks site cleanup and restoration will be completed.
Full road construction is expected to start mid-July. The project page for the current projects can be found here: https://www.stcharlesil.gov/projects.
Martam Construction will continue to pre-dig and locate utilities along IL Rte. 31 and Roosevelt Street during the week of April 26th and May 3rd.
Tree removal and trimming will start the week of May 10 and will be conducted by Homer Tree Services. Maps of the tree trimming and removal can be found under project documents.
TUESDAY, APRIL 27
7th Avenue at South Ave. will be down to one lane with flaggers for the day.
Installation of box culvert sections on South Ave.
Horizontally drilled sewer pipe between Illinois and Indiana
Grading and stabilization of creek side slopes south of South Ave.
Sanitary sewer replacement on South Ave.
Water Main replacement on South Ave. – Impacted residents will receive notification in advance of any shutdowns.
South Ave. box culvert preparations
General site maintenance