Phase One utility repairs have been completed on all streets.

Phase Two curb and sidewalk repairs have completed on all streets except Ohio Avenue.

Phase Three pavement replacement has been completed on all streets except Ohio Avenue.

Work on Phase Two and Three improvements will continue on Ohio Avenue this week.

Parkway restoration has been done or is taking place on all streets except Ohio Avenue.

 