Update - 7/17/23

Anticipated construction work for the week of July 16 – July 22

Please Note: All work contingent on weather, street access will be maintained during asphalt milling.

East Side Streets

  • Fox Chase Blvd. – Landscape restoration, potential asphalt milling
  • Hampton Course – Landscape restoration
  • Lexington Ave. – Final watermain connection. Valve and hydrant replacements.  Scheduled water shutdown for Monday 7/17. Concrete restoration to begin.
  • Lancaster Ave. – Concrete restoration to begin
  • Liberty Ave. – Concrete restoration to begin
  • Liberty Ct. – Concrete restoration to begin
  • Cranbrook Ave. – Concrete restoration to begin

West Side Streets

  • River View Dr. – Asphalt milling, driveway repairs
  • River Ridge Dr. – Asphalt milling, driveway repairs
  • Prairie Crossing Dr. – Asphalt milling, driveway repairs
  • Renard Ln. – Asphalt milling, driveway repairs
  • Voltaire Ln. – Asphalt milling, driveway repairs
  • Provence Dr./Ct. – Asphalt milling, driveway repairs
  • Antoine Pl./Ct. – Asphalt milling, driveway repairs
created Jul 17, 2023 updated Jul 17, 2023