Week of July 15, 2013

Underground utility work continues with the installation of storm sewer pipe, and excavation for and installation of approximately 140 feet of 4” SDR 35 sleeve for the new gas service to the new building.

Walls for the first two floors of the south end of the building and storage tanks have been erected as well as the truck bay area.  Additional work completed aligning the exterior Aeration Basin Blowers on the equipment pad east of the existing building.

Week of July 8, 2013

Paving has been completed on South 4th Ave, Independence Ave, Concord Ct, Williams Ave, Allen Ln, Post Rd and Wing Ln. Final cleanup and parkway restoration is planned to take place on these streets this week.

Utility work on South 7th Street started on July 2 and is to continue this week. Utility work will consist of repairs to water mains, fire hydrants, storm sewers, and sanitary sewers.