Week of July 15, 2013

Utility work on South 7th Street started on July 2 and is to continue this week. Utility work will consist of repairs to water mains, fire hydrants, storm sewers, and sanitary sewers.

Concrete contractor is scheduled to remove and replace curb and sidewalk on South 7th Street late this week.

The grinding, resurfacing and striping of public parking lots at the southeast corner of Second Street (Route 31) and West Main Street, and at the northwest corner of Third Avenue and East Main Street is now complete.

For the Week of July 15, 2013

Restoration work on the Municipal Building continues on schedule this week.  Masonry work along the east elevation of the Old City Hall and South Annex building has been completed. Replacement of the limestone base and stone copings will be complete in approximately a week once the stone is delivered from the quarry. All of the scaffolding along the east elevation has been removed and the public sidewalk re-opened.

Week of July 15, 2013

Underground utility work continues with the installation of storm sewer pipe, and excavation for and installation of approximately 140 feet of 4” SDR 35 sleeve for the new gas service to the new building.

Walls for the first two floors of the south end of the building and storage tanks have been erected as well as the truck bay area.  Additional work completed aligning the exterior Aeration Basin Blowers on the equipment pad east of the existing building.

Week of July 8, 2013

Paving has been completed on South 4th Ave, Independence Ave, Concord Ct, Williams Ave, Allen Ln, Post Rd and Wing Ln. Final cleanup and parkway restoration is planned to take place on these streets this week.

Utility work on South 7th Street started on July 2 and is to continue this week. Utility work will consist of repairs to water mains, fire hydrants, storm sewers, and sanitary sewers.