You are here

Construction

July 2, 2012

Work continues at the northeast corner of the new bridge near the intersection of East Main Street and Powis Road. Numerous utility conflicts have been encountered and relocation work for these items will be required. To read the full update, download the attached document.

July 2, 2012

Most of the scheduled work and street repair work has been completed and South 4th Street will be open to traffic June 29, 2012. Disturbed areas have been prepared for sod that will be placed as weather permits.

All residents that are within the affected construction limits have received notification letters describing the projects limits, and anticipated work activities. The city has delivered sod maintenance letters asking residents to assist with watering of new sod whenever possible.

Week of June 25, 2012

Meade Electric will continue to work on the installation of the temporary traffic signals throughout the project. Meade will also be working on the adjustment of an existing electrical vault on Smith Road just north of East Main Street. Once this work is completed the contractor will complete the remaining curb work on the east side of Smith Road and begin working on the west side.  To read the full update, download the attached document.

Week of June 25, 2012

Most of the scheduled work has been completed and South 4th Street is currently open to traffic. Repairs of some sections of concrete pavement are anticipated to take place this week.

The contractor has been informed that emergency vehicles must have access to residential properties at all times.

All residents that are within the affected construction limits have received notification letters describing the projects limits, and anticipated work activities.

Week of June 18, 2012

Most of the scheduled work has been complete and South 4th Street is anticipated to be open for traffic on June 15.

The contractor has been informed that emergency vehicles must have access to residential properties at all times.

All residents that are within the affected construction limits have received notification letters describing the projects limits, and anticipated work activities.

Week of June 18, 2012

The Contractor has begun lane closures near the intersection of East Main Street and 7th Avenue and will be expanding these lane reductions easterly towards Hunt Club Drive. Work is expected to be at this location for the next few weeks, focusing on watermain installation, sanitary service repairs, and storm sewer work. In addition, private utility companies such as NICOR Gas, AT&T and ComEd will be working on relocating their infrastructure.

To read the full update, download the attached document

Engineering Design & Inspection Policy Manual

Pages