Week of July 27, 2015
The work completed for the week ending July 25, 2015 included the Allen Lane connection as well as the fire hydrant installation at this location. The connection at North Avenue was also completed with the associated fire hydrant. Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts. Contractor has begun restoration of curb and gutter.