You are here

Construction

Update - 8/3/16

The contractor will continue this week with the grading of the parkway areas, placing topsoil and adjustment of the utility structures in the roadway to the final pavement elevation.  The week of 8/8, the contractor will be placing fresh oil on the roadway in preparation for the final pavement surface with the pavement marking to follow.  If weather cooperates, we anticipate the roadway work to be completed by 8/12.  The sod restoration work is anticipated to take place in early September.

Update - 8/3/16

The remainder of this week and into next week the contractor will be working on installing the aggregate shoulder, grading the parkway where needed and restoration.  The final roadway striping will be placed next week and the project will be completed.

Pages