Update - 7/8/16
The work for th is project is anticipated to start the week of July 11th, with completion in mid-August.
The work for th is project is anticipated to start the week of July 11th, with completion in mid-August.
This week, the water main was successfully pressure tested. In addition, EEI staked out the access road. WJ Johnston will be working on getting the road graded, and they anticipate beginning the drainage swale improvements adjacent to the site at some point next week.
Update - 6/30/16
The work proposed for the week of July 4th includes:
The work proposed for the week of July 4th includes:
Painting of the water tower has been completed.
The watermain has been installed from the tank to the existing stub; site work and pressure testing will continue this week.
Due to unforeseen circumstances the Red Gate Road Resurfacing project has been delayed and will not be starting construction the week of June 25th. More information will be posted on the City’s project website on the status of this project when it becomes available.
The work proposed for the week of June 27th includes:
Brush Pick-Up – This area is scheduled for brush pick up the week of June 20th and will continue as planned. All brush material should be placed in the parkway outside of the area that the contractor is working. Any questions, please contact the Public Works Department at 630-377-4486.