Construction
Update - 5/23/16
The Contractor will be on site working on punch list items this week.
South Tyler Road Rehabilitation Project Notification Packet
Illinois Bridge Notification
Update - 5/12/16
The contractor is wrapping up the landscape planting for this project and it is anticipated that the project will be completed shortly. Once the project is completed, the City will monitor the establishment of the plant material for project acceptance.
Update - 5/9/16
The water tower contractor has finished the abrasive blast cleaning on the interior wet surfaces and is in the process of applying the prime coat to all the interior surfaces. The painting of the exterior has begun and the contractor has started to apply the intermediate coat to the exterior. Painting will continue on both the interior and/or exterior depending on the weather conditions over the next several weeks, followed by final site work, landscaping and paving work.
Riverside Avenue Resurfacing Project Available Parking
Project Update for March 11, 2016
Martam Construction will be on site starting next week to finish the punch list items that could not be completed during the winter months, including adjustment of water service b-boxes, installation of water service locating equipment for the properties along IL Route 25 and clean-up/restoration throughout the entire project.
Week of December 21, 2015
The contractor has completed all of the main work for this project and will continue to work on punch list items as the weather allows. The landscape restoration has been completed for the majority of the project area. The City will be completing a complete landscape inspection in the spring after the temperatures are warm enough to allow the grass seed that was planted to grow and ample time for the areas to fill in appropriately. Once this final landscaping inspection is completed the contractor will repair any areas that need attention. Updates for this project will only be posted du
Week of December 7, 2015
All roadway paving work was completed last week. The contractor will be out this week working on landscape restoration and other miscellaneous remaining items. There will be lane closures during this work and flaggers will be directing traffic around the work during this time.