Week of August 10, 2015
Check back in Spring 2016 for project updates.
Check back in Spring 2016 for project updates.
Avalon Court
No work this week.
8th Street and 8th Court
No work this week.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week.
Walnut Ave.
Concrete pavement base. HMA pavement grinding. Brick sidewalk repair.
Crabapple Ln.
No work this week.
S. 10th Ave
Concrete sidewalk repair.
Work for the week of August 10 is as follows:
Crack prevention material placement (Petromat)
Hot Mix Asphalt - roadway surface placement
Restoration behind new curb and sidewalks
The work completed for the week ending August 1, 2015 included starting on the Marion Avenue connection as well as the fire hydrant installation at this location. Flushing and pressure testing of the new watermain has begun. The contractor has begun restoration of curb and gutter.
Work for the week of August 3 is scheduled as follows:
Restoration behind new curb and sidewalks
Crack prevention material placement (Petromat)
Hot Mix Asphalt - roadway surface placement
Avalon Court
Paving complete, Restoration September 1st.
8th Street and 8th Court
Paving complete, Restoration September 1st.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Paving complete, Restoration September 1st.
Walnut Ave.
No work this week.
Crabapple Ln.
Paving complete, Restoration September 1st.
Avalon Court
Hot Mix Asphalt, leveling binder and crack prevention material
8th Street and 8th Court
Hot Mix Asphalt, leveling binder and crack prevention material
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Hot Mix Asphalt, surface and crack prevention material
Walnut Ave.
Concrete street repair and patching
The work completed for the week ending July 25, 2015 included the Allen Lane connection as well as the fire hydrant installation at this location. The connection at North Avenue was also completed with the associated fire hydrant. Flushing and pressure testing of the new watermain has not yet been scheduled due to delivery of needed parts. Contractor has begun restoration of curb and gutter.
Work for the week of July 27 is scheduled as follows:
Hot Mix Asphalt - leveling binder placement
Structure adjustments in roadway pavement
Traffic signal loops at Route 64
Roadway ditch grading north of Voltaire Lane
Crack prevention material placement (Petromat)
Work scheduled for Friday, July 24 and Saturday, July 25 is scheduled as follows:
Pavement prime coat (Fresh Oil) being placed at sunrise on Saturday.
Concrete curb and sidewalk saw cutting, forming and pouring new concrete curb and sidewalks.
Utility structure adjustments.
Pavement grinding and pavement patching, mid-week through the end of the week.