Week of October 12, 2015
The work completed for the week ending October 10, 2015 included the start of replacing all electrofused fittings on the HDPE pipe. The new valve and valve vault to the golf course was installed this week as well.
The work completed for the week ending October 10, 2015 included the start of replacing all electrofused fittings on the HDPE pipe. The new valve and valve vault to the golf course was installed this week as well.
Avalon Court
Completed – Punchlist items outstanding
8th Street and 8th Court
Completed – Punchlist items outstanding
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed
Walnut Ave.
Completed – Punchlist items outstanding
Crabapple Ln.
Completed – Punchlist items outstanding
S. 10th Ave
Completed – Punchlist items outstanding
Stone Dr. and DuKane Dr.
The contractor will begin work next week to start to remove the trees necessary to complete the streambank restoration work. In the following weeks they will be working on grading the channel and banks and installing stabilization measures along the creek.
Due to the scope and complexity of this project, weather delays, and some unforeseen circumstances, project completion has been pushed back to later this fall. The contractor has worked to make some repairs to he temporary patches on N. 5th Avenue to provide a smoother driving surface. They have also worked to clean up the right-of-way and other work areas, removing debris and construction materials that will are not needed for future work. The contractor will continue to work on the watermain along N.
Avalon Court
Minor sidewalk repair.
8th Street and 8th Court
Completed – Punchlist items outstanding.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed
Walnut Ave.
Completed – Punchlist items outstanding.
Crabapple Ln.
Minor sidewalk and curb repair.
S. 10th Ave
Completed – Punchlist items outstanding.
Stone Dr. and DuKane Dr.
Tyler Road
The work completed for the week ending September 19, 2015 included the installation of all watermain from Allen Lane to IL 64. Testing and chlorination of the watermain and installation north of Wing Lane is complete.
The scheduled work for the week ending September 26, 2015 will include the continued testing and chlorination installation of watermain to the south of Wing Lane and the installation of services. Restoration including concrete work will begin.
The work completed for the week ending September 19, 2015 included working on flushing and testing of watermain north of the cemetery. Repairs on the watermain in the area continue. Cleanup efforts on the project site continue.
Tyler Road
The work completed for the week ending September 12, 2015 included the installation of watermain from Wing Lane to south of the school. Chlorination of the watermain began on the north end of the project.
The scheduled work for the week ending September 19, 2015 will include the continued installation of watermain to the south and the installation of services on the north.
The work completed for the week ending September 12, 2015 included working on flushing and testing of watermain north of the cemetery. Drilling for the connection of the watermain to the maintenance shed at the St. Charles Country Club will also occur. Cleanup efforts on the project site continue.
Tyler Road
The work completed for the week ending September 5, 2015 included the installation of watermain from Allen Lane south to Wing Lane. Flushing and pressure testing of the watermain began on the north end of the project.
The scheduled work for the week ending September 12, 2015 will include the continued installation of watermain to the south.