You are here

Construction

Week of October 12, 2015

West Side of Fox River

Avalon Court
Completed – Punchlist items outstanding

8th Street and 8th Court
Completed – Punchlist items outstanding

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed    

East Side of Fox River

Walnut Ave.
Completed – Punchlist items outstanding

Crabapple Ln.
Completed – Punchlist items outstanding

S. 10th Ave
Completed – Punchlist items outstanding

Stone Dr. and DuKane Dr.

September 30, 2015

The contractor will begin work next week to start to remove the trees necessary to complete the streambank restoration work. In the following weeks they will be working on grading the channel and banks and installing stabilization measures along the creek.

Week of September 28, 2015

Due to the scope and complexity of this project, weather delays, and some unforeseen circumstances, project completion has been pushed back to later this fall. The contractor has worked to make some repairs to he temporary patches on N. 5th Avenue to provide a smoother driving surface. They have also worked to clean up the right-of-way and other work areas, removing debris and construction materials that will are not needed for future work. The contractor will continue to work on the watermain along N.

Week of September 28, 2015

West Side of Fox River

Avalon Court
Minor sidewalk repair.

8th Street and 8th Court
Completed – Punchlist items outstanding.

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed      

East Side of Fox River

Walnut Ave. 
Completed – Punchlist items outstanding.

Crabapple Ln.
Minor sidewalk and curb repair.

S. 10th Ave
Completed – Punchlist items outstanding.

Stone Dr. and DuKane Dr.

Week of September 21, 2015

EAST SIDE OF FOX RIVER

Tyler Road
The work completed for the week ending September 19, 2015 included the installation of all watermain from Allen Lane to IL 64.  Testing and chlorination of the watermain and installation north of Wing Lane is complete.

The scheduled work for the week ending September 26, 2015 will include the continued testing and chlorination installation of watermain to the south of Wing Lane and the installation of services.  Restoration including concrete work will begin.

Week of September 14, 2015

EAST SIDE OF FOX RIVER

Tyler Road
The work completed for the week ending September 12, 2015 included the installation of watermain from Wing Lane to south of the school. Chlorination of the watermain began on the north end of the project.

The scheduled work for the week ending September 19, 2015 will include the continued installation of watermain to the south and the installation of services on the north.

Week of September 14, 2015

The work completed for the week ending September 12, 2015 included working on flushing and testing of watermain north of the cemetery. Drilling for the connection of the watermain to the maintenance shed at the St. Charles Country Club will also occur. Cleanup efforts on the project site continue.

Week of September 7, 2015

EAST SIDE OF FOX RIVER

Tyler Road
The work completed for the week ending September 5, 2015 included the installation of watermain from Allen Lane south to Wing Lane. Flushing and pressure testing of the watermain began on the north end of the project.

The scheduled work for the week ending September 12, 2015 will include the continued installation of watermain to the south.

Pages