Week of September 7, 2015
The work completed for the week ending September 5, 2015 included completion of all watermain. Working on flushing and testing of watermain north of the cemetery. Cleanup efforts on the project site continue.
The work completed for the week ending September 5, 2015 included completion of all watermain. Working on flushing and testing of watermain north of the cemetery. Cleanup efforts on the project site continue.
The work completed for the week ending August 29, 2015 included the cleaning and televising of the watermain on the south end of the project. Pouring of curb and gutter between Marion Avenue and north of the cemetery as well as permanent patching north of Stonehedge Road occurred this week. Cleanup efforts on the project site continue.
Avalon Court
No work this week. Restoration 1st and 2nd week of September.
8th Street and 8th Court
No work this week. Restoration 1st and 2nd week of September.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week. Restoration 1st and 2nd week of September.
Avalon Court
No work this week
8th Street and 8th Court
No work this week
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week
Walnut Ave.
Hot Mix Asphalt roadway surface pavement paving.
Crabapple Ln.
No work this week.
S. 10th Ave
Hot Mix Asphalt roadway surface pavement paving.
Stone Dr. and DuKane Dr.
All work is completed at this time except for punch list items.
The work completed for the week ending August 22, 2015 included the connection between North and Iroquois Avenues. The contractor has cleaned and televised the watermain for investigation of debris and is in the process of making necessary repairs. Cleanup efforts on the project site continue.
Work for the week of August 17 is as follows:
Placement of pavement striping
Placement of roadway shoulder at north end of project
Placement of driveway aprons
Placement of topsoil with seed and seed blanket behind new curb and sidewalks
The work completed for the week ending August 15, 2015 included the connection at Marion Avenue. The contractor televised a section of the watermain for investigation of debris and performed heavy cleaning of the watermain using a swabbing device. Cleanup efforts on the project site continue.
The scheduled work for the week ending August 22, 2015 will include the re-televising of the watermain prior to flushing and pressure testing to assure that the line has been cleaned thoroughly.
Avalon Court
No work this week.
8th Street and 8th Court
No work this week.
Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
No work this week.
Walnut Ave.
Hot Mix Asphalt pavement grinding.
Hot Mix Asphalt pavement paving.
Crabapple Ln.
No work this week.
S. 10th Ave
Hot Mix Asphalt pavement grinding.
Hot Mix Asphalt pavement paving.
Check back in Spring 2016 for project updates.