You are here

Project News

8/9/19 Update

  1. The final clean is on going and will continue until the last coast of paint goes on.
  2. The remainder of the millwork has arrived ad has been installed.
  3. The last remaining epoxy work will be in the squad garage, but all other spaces are complete.
  4. The squad garage has been painted and is currently being prepped for epoxy.
  5. Furniture install is ongoing and looks fantastic. Its exiting to see the spaces come to life with it.

Update - 8/5/19

This week the contractor will be pouring concrete curbs and sidewalks, paving the asphalt binder course and adjusting structures in the roadway.  Next week the contractor will complete the asphalt surface course.  Landscape restoration will be ongoing.

Update - 8/5/19

Update 8/05/19 – Anticipated construction work for the week of August 5-9

East Side Streets

  • Cedar Avenue – Concrete sidewalk and curb
  • Fieldgate Road – No work at this time
  • Majestic Oaks Drive – Roadway fabric and asphalt surface
  • State Avenue – Concrete sidewalk and curb

West Side Streets

8/2/19 Update

  1. The exterior signage continues to be installed and final electrical connections made.
  2. The landscaping work is continuing with the main focus being on trees now. Next come the grasses and sod.
  3. The monument sign masonry base at the 15th street entrance drive is being built today and the actual sign is ready to be delivered as soon as it is complete.
  4. The millwork paneling is going up at the main stair and should be complete by end of day Saturday. The signage there will go on immediately afterwards.
  5. The squad garage is the last area to be completed.

Update - 7/25/19

Anticipated construction work for the week of July 29- August 2

East Side Streets

  • Cedar Avenue – Sawcutting ,concrete removal and replacement
  • Fieldgate Road – No work at this time
  • Majestic Oaks Drive – Milling asphalt, paving asphalt surface
  • State Avenue – Sawcutting ,concrete removal and replacement

West Side Streets

Pages