You are here

Project News

Update - 7/24/19

The storm sewer replacement work is complete.  The contractor is working on clean up and site preparation in the rear yards of Matisse Drive this week for the landscape restoration which is scheduled for next week.  Tree replanting will take place in early fall when the weather is more suitable for a successful transplant.

7/19/19 Update

  1. The decorative fencing has started. The temporary fence is mostly removed from the site.
  2. The generator has been set. The work to tie it into the building will take place tomorrow with the manufacturer startup happening next week.
  3. The flooring upstairs now has the tactile warning installed.
  4. The first floor lobby soffits are complete with all subcontractors out the space (less the final security camera install) so the flooring can be installed.
  5. The ceramic tile has started in the lobby and west storm shelter.

 

Update - 7/19/19

Next week the contractor will begin landscape restoration and install the new cured-in-place liner on the old sanitary sewer main. Landscape restoration and contract punch list items will continue into early August.

Update - 7/18/19

Anticipated construction work for the week of July 22-26:

East Side Streets

  • Cedar Avenue – Sawcutting for concrete removals, patching asphalt
  • Fieldgate Road – No work at this time
  • Majestic Oaks Drive – Milling asphalt
  • State Avenue – Sawcutting for concrete removals, patching asphalt

West Side Streets

7/12/19 Update

  1. The permanent fencing has started on the south side of the project. The temporary will remain for a short time until we have a substantial amount in place to keep a level of security.
  2. The rip rap (larger stone typically placed at various utility structures – in our case the pond inlets and outlets) has been placed at the pond and the native plugs have been holding nicely.
  3. The first and second phases of epoxy floors are complete.

Update 7/12/19

Anticipated construction work for the week of July 15-19

 East Side Streets

  • Cedar Avenue – Sawcutting for concrete removals, milling asphalt, patching asphalt
  • Fieldgate Road – No work at this time.
  • Majestic Oaks Drive – Milling asphalt
  • State Avenue – Sawcutting for concrete removals, milling asphalt, patching asphalt

West Side Streets

Update - 7/12/19

Storm sewer work on Deville will conclude this week.  Additional concrete work will be completed prior to road resurfacing in the coming weeks.  Storm replacement will immediately transition to rear yards between Picasso Drive and Monet Place.  On Friday, July 12th and Monday July 15th, fence and landscape removal will take place in rear yards along Mattise Drive to prepare for the next phase of the storm sewer replacement project.

7/5/19 Update

  1. The garage ADA ramp has been poured which means we can now start to move trades out of that space to prep for the epoxy.
  2. The detention fixtures are being installed and the specialty plank ceilings are in the final stages of completion.
  3. The storm shelter shrouds are installed as I mentioned above.
  4. These cover the 90 degree bends that all of the mechanical piping coming into the storm shelter makes.

Update 7/3/19

Anticipated construction work for the week of July 8-12

East Side Streets

  • Cedar Avenue – No work at this time.
  • Fieldgate Road – No work at this time.
  • Majestic Oaks Drive – No work at this time.
  • State Avenue – No work at this time.

West Side Streets

Pages