Project News

Week of September 8, 2014

ALamp will be relocating the three monuments on Tuesday. They expect to be grading the site and forming for curb and gutter on Wednesday, and the first sections of curb will be poured on Thursday / Friday.

Subsequent to monument relocation the plaza area will be excavated and brought to grade for placement of the seat wall and stairs.

Week of August 25, 2014

Paving and leving binder will be put put down Tuesday and Wednesday of this week. 

Utility structure adjustments in the pavement and restoration of disturbed landscape areas will begin at the end of this week and continue into next week.   

Final surface paving will begin the middle of the next week.  

Week of August 25, 2014

ALamp pressure tested and chlorinated the water main and will be sampling the water main this week.

Electric conduit installation has begun and they expect to finish electrical conduit installation.

ALamp will excavate and install the monument foundations and install irrigation tap and put new water main in service (Saturday 8.30.14).

Week of August 18, 2014

Pavement grinding work performed by Geneva Construction crews has commenced as of August 14, 2014 and is expected to continue through the end of the week.

Geneva Construction is scheduled to place a leveling binder course of hot-mix asphalt on Tyler Road and repair driveway aprons prior to the first day of school, August 20, 2014.